The works briefly comprise: • Installing Traffic Management • Removing surfacing and expansion joints • Excavating behind abutments • Removing back of wall drainage layer • Hydro-demolition of top of ballast wall • Re-casting top of ballast wall & nib • Installing new expansion joints and waterproofing • Reinstating back of wall drainage layer • Backfilling behind abutments • Resurfacing incl. road markings • Removing Traffic Management The Contractor to provide all necessary transport, tools, access equipment, appropriate welfare, water disposal and clearance on completion in order to carry out the works effectively.
Details
- What the buyer calls it
- 0680 Country Park Bridge Works Contract 2025
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Where
- in the North West
Who the buyer named
Anthony Baker was the named contact on this notice. Questions closed on 13 Jun 2025, 12:00 BST.