The property consists of 2 small retail units on the ground floor with 3 residential units above. The Council undertook the rebuilding of this property in 2015/16 due to the fact that it had suffered, and continued to suffer, extensive subsidence. This was to the extent that 154 was deemed as unsafe and that the remaining properties were close to being uninhabitable. Unfortunately, the main contractor appointed to carry out the building works went into liquidation prior to the works being completed. In addition to this, it was subsequently identified that the works did not wholly conform with the planning permission in existence at that time. The Council has since successfully …
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- 148-154 Stoke Newington Church Street
- How they are buying
- Given to one supplier, no competitionNobody else was asked, and the buyer has to be able to justify that.
- Type
- works
- Work starts
- 17 Jun 2019
- Work ends
- 13 Sep 2019
- Kind of work
- Construction
Who the buyer named