The United Kingdom Atomic Energy Authority are looking to engage a Supervisory Control And Data Acquisition (SCADA) specialist to develop a new SCADA system in J5 based on the IEC 61850 protocol, replacing the existing SCADA. The 400/33kV substation, the existing control and automation system, comprising historic CODAS system, SCADA and Programmable Logic Controllers, will be decommissioned and replaced with an advanced site-wide master SCADA system in full compliance with the IEC 61850 protocol. The work includes the design, manufacture, delivery, installation, and commissioning of the complete system, including an operator workstation in J5 control room. The SCADA will provide full control…
Details
- What the buyer calls it
- 33kV Substation SCADA Supply
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- goods
- Where
- in the South East
- Kind of work
- Street lighting and energy infrastructure
Asking a question
Ben Grainger is the named contact on this notice. Questions closed on 12 Oct 2026, 17:00 BST.
Above threshold you will be asked for a PPON and a share code when you bid. Getting one takes about half an hour, once.