5060-3-Estates-SE-RFI HMP North Sea Camp New Sewer Connection CR BPRN 579/03/8446 Stages 4-7
What the buyer wrote
5060-3-Estates-SE-RFI HMP North Sea Camp New Sewer Connection CR BPRN 579/03/8446 Stages 4-7
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- 5060-3-Estates-SE-RFI HMP North Sea Camp New Sewer Connection CR BPRN 579/03/8446 Stages 4-7
- How they are buying
- Given to one supplier, no competitionNobody else was asked, and the buyer has to be able to justify that.
- Work starts
- 24 Feb 2016
- Work ends
- 18 Mar 2019
- Kind of work
- Construction, Water, drainage and flood management
Who the buyer named
Simon Cadby was the named contact on this notice.