What the buyer wrote
Alison Gingell was built and handed over in 2017, there remains one fallow space on the third floor which is due to be fitted to provide a Radiography Suite to include a classroom, ultrasound room and radiography room. It is for this purpose Coventry University require a suitably competent contractor to carry out the construction works to create the space and management of the radiography machine installation by third party subcontractors.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Alison Gingel Refurb - AWARD
- How they are buying
- Advertised, shortlist firstSuppliers applied to be considered, and the buyer picked who went on to bid.
- Type
- works
- Work starts
- 3 Aug 2020
- Work ends
- 30 Oct 2020
- Kind of work
- Building maintenance and repairs
Who the buyer named
ADMINISTRATOR was the named contact on this notice.