Barbican Renewal Programme - Demolition and Structures
What the buyer wrote
Demolition and Structures — Barbican Renewal Programme. Refurbishment and alteration to an existing, occupied Grade II listed Brutalist concrete building (1965–1982) — not new-build; minimal structural intervention philosophy, using existing capacity and justifying retained elements without strengthening wherever possible. The project comprises demolition, enabling, temporary works and primary structural design and construction across the Renewal Phase 1 work areas, together with a sitewide Contractor Design Portion (CDP) framework covering secondary/tertiary steelwork, non-loadbearing masonry, builders work openings, steel reuse and other structure-adjacent design responsibilities. This pac…
Details
- What the buyer calls it
- Barbican Renewal Programme - Demolition and Structures
- How they are buying
- Advertised, then negotiatedThe buyer talked terms with bidders rather than taking fixed offers.
- Type
- works
- Where
- in London
Asking a question
The buyer published a contact address on this notice. Questions closed on 9 Oct 2026, 12:00 BST.
andrew.stirland@cityoflondon.gov.uk
Above threshold you will be asked for a PPON and a share code when you bid. Getting one takes about half an hour, once.
You submit through the buyer’s own system: Jaggaer, Jaggaer.