The purpose of the ITT is to obtain professional, properly defined and priced propositions for a Principal Contractor for the installation of the Property Level Protection under the NEC3 Engineering & Construction Contract 3rd Edition, Option A.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- BHCC DR Central Hove and Portslade Property Level Protection Scheme: Principle Contractor - AWARD
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Work starts
- 30 Oct 2018
- Work ends
- 31 Mar 2019
- Kind of work
- Construction
Who the buyer named
Rod Walters (ADC/CDC) was the named contact on this notice.