To isolate hot and cold water supplies. Supply and fit temperature gauges on HWS flow and return pipework. To fit expansion vessel in correct orientation complete with new bracket. Service all thermostatic mixing valves, clean strainers and set at 41°c. To descale outlets noted on report. Check all calorifiers and point of use water heaters and set temperatures at 60°c. To supply and fit new single check valve. Remove dead legs as detailed on legionella report and cap off at parent pipes or straight line pipework. Adjust pressure to boys toilet taps To isolate and strip out all braided pipework to taps and replace with solid copper pipework as per regulations.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Industrial Pipe Services£8kends (31 Jul 2018)

Details

What the buyer calls it
Booker Hill School - Legionella Works
How they are buying
Advertised, shortlist firstSuppliers applied to be considered, and the buyer picked who went on to bid.
Type
works
Suitable for small firms
The buyer says yes. What that is worth
Work starts
21 Jun 2018
Work ends
31 Jul 2018

Who the buyer named

Emily Everton was the named contact on this notice.