What the buyer wrote
The Authority has undertaken a 2-stage mini-competition from the Southern Construction Framework (SCF) and entered into a pre-construction agreement (PCSA) for the demolition and construction of a new fire station at its Brixham Fire Station site. This award notice is to publish details of the expenditure made on two instructions whilst under the PCSA with the contractor. Additional information: Expenditure under PCSA relates to two PCSA Instructions. Whilst an 'end date' has been provided, this is for the financial year end of the year in which the PCSA has been commenced. The end date for the PCSA is an unknown timescale and will be subject to the final build cost and the formal award o…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Brixham Fire Station - PCSA - Demolition & New Build
- How they are buying
- Called off an existing agreementThe work went to a supplier already on a framework or dynamic market.
- Type
- works
- Work starts
- 24 Jul 2019
- Work ends
- 31 Mar 2020
- Kind of work
- New build construction, Civil engineering and groundworks
Who the buyer named