The mains works for the scheme are to improve the current condition of the approach footpaths (re-construct)and replace the ornate railings that are in a poor condition. Large pre-cast L shape retaining wall sections are to be constructed to form the new retaining wall while maintaining the existing walls with improvement works. Drainage works and minor maintanance work will also be included in the scheme for all the current infastructure.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- C2401 Trinity Cut, Bridlington
- How they are buying
- The buyer did not say
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 13 Oct 2019
- Work ends
- 27 Jan 2020
- Kind of work
- Construction, Water, drainage and flood management