Construction Plan 1. Scope of Works. The works will include: • Site preparation and demolition of existing fence. • Earthworks, grading and sub-base preparation. • Installation of drainage systems. • Construction of reinforced concrete skatepark elements (bowls, ramps, platforms, coping). • Installation of street-style features (rails, ledges, stairs). • Perimeter works including pathways and landscaping. • Site clean-up, quality checks, and handover. 2. Methodology 2.1 Mobilisation • Establish site compound, temporary fencing and signage. • Set out works in accordance with approved design drawings. • Conduct pre-start meetings with subcontractors and suppliers. 2.2 Site Preparation • Clear …