As a part of the Castleford to Wakefield Greenway scheme a cycleway bridge is required to cross the existing railway. The crossing position is at the position of an existing bridge which has since been removed. Abutments remain but these are not to be utilised in the design, though the effect of their possible removal must be considered by the designer. The feasibility report has recommended a 35m span steel bridge on abutments independent and not reliant on the existing abutments. The contractor is to design and build a 35m span steel cycleway bridge in accordance with the current Design Manual for Roads and Bridges and the Manual of Contract Documents for Highway Works as published…

Read all of it on Contracts Finder →

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Amalgamated Construction Ltd£420.9kends (9 Jun 2019)

Details

What the buyer calls it
Castleford to Wakefield Greenway Cycleway Bridge Over Live Railway.
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
23 Sep 2017
Work ends
9 Jun 2019

Who the buyer named

The buyer published a contact address on this notice.

procurement@wakefield.gov.uk