The project consists of 175 New Build Residential units over 5 blocks with 4 commercial units to the ground floors. Piled foundations, RC frames and different envelope types. The project duration is 140 weeks, start date is 17th August 2020 with anticipated completion on 24th June 2023. Claritas Group is the Construction manager and any successful Contract will be let between Medway Council and the Trade Contractor. This opportunity is for the appointment of an Architectural Metalwork Contractor. Expressions of Interest must be made via the Kent Business Portal. Tenders will not be accepted via any other route and procurement documents are not available other than by expressing an interest …

Read all of it on Contracts Finder →

Details

What the buyer calls it
Chatham Waterfront - Architectural Metalwork - secured project
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Suitable for small firms
The buyer says yes. What that is worth
Work starts
4 Jan 2022
Work ends
4 Mar 2022

Who the buyer named

Mike Kelly was the named contact on this notice.