What the buyer wrote
Replacement of Boilers, Internal Classroom Structural Alterations and Fire Precautions Works at Cowes Primary School The term of the contract shall be 10 weeks, from 24th June 2019 until 30th August 2019. Works to the Boilers have been programmed such that a proportion can be carried out during the school term, see the contract drawings for details.
Details
- What the buyer calls it
- Cowes Primary School Boiler Replacement and Internal Remodelling
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 23 Jun 2019
- Work ends
- 30 Aug 2019
Who the buyer named
Mrs Claire Sarr was the named contact on this notice.