CPU 1606 - Construction and installation of a new substation and demolition of old substation.

Your saved contracts

What the buyer wrote

Construction and installation of a new substation and demolition of old substation. at Palmerston Gardens, Nottingham NG3 1DY, (off Shelton Street).

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

vital energi£329.9kends (31 Dec 2016)

Details

What the buyer calls it
CPU 1606 - Construction and installation of a new substation and demolition of old substation.
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Suitable for small firms
The buyer says yes. What that is worth
Work starts
18 Jun 2016
Work ends
31 Dec 2016

Who the buyer named

Ms Penny Taylor-Jones was the named contact on this notice.

Penny.Taylor-Jones@nottinghamcity.gov.uk