What the buyer wrote

The Babbage building is located on the main campus and will be undergoing a complete refurbishment along with some new additional elements, starting early July 2020. In its place the University is planning on creating a New Engineering and Design Facility which will house variety of flexible teaching spaces for various faculties and student use. Due to the work carried out on site there is a requirement for relocation of Data Centre currently based in room 015 in Babbage building to room B008 at Portland Square building. The University is therefore looking to procure a contractor to design, supply and fit a complete solution resulting in the creation of a new Data Centre Facility within Port…

Read all of it on Contracts Finder →

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Totus Engineering (Holdings) Limited£474kends (15 Jul 2020)

Details

What the buyer calls it
Data Centre Relocation
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
10 Feb 2020
Work ends
15 Jul 2020

Who the buyer named

Procurement Procurement was the named contact on this notice.

procurement@plymouth.ac.uk