What the buyer wrote
The supply, delivery, design, supply of rigs and installation of Sheet Piling for the Deptford Site. Approximately 120 linear metres at 15-20m depth. Civil Engineering and Tunnelling - The Main Contract works comprises the East Tunnelling section of Tideway Tunnel with works being undertaken at the main drive site Chambers Wharf, CHAWF, running East to Abbey Mills taking into shafts and tunnelling works at Deptford Church, DEPCS, King Edward Memorial Park Foreshore, KEMPF, Earl Pumping Station , EARPS, and Abbey Mills reception site. Greenwich Pumping Station and spur tunnel works provide the link to the East Tideway Tunnel. …
Details
- What the buyer calls it
- Deptford Sheet Piling
- How they are buying
- The buyer did not say
- Type
- goods
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 1 Mar 2021
- Work ends
- 5 Apr 2021
Who the buyer named
Gary Peck was the named contact on this notice.