What the buyer wrote

To appoint a sub-contractor to carry out all adopted roads and drainage works as part of the Ellington Phase 2 works which comprises 69 new build dwellings at the former Ellington Colliery, Lynemouth Road, Ellington. The works include the completion of adopted roads and footpaths, adopted drainage, both foul and service and service trenches and duct work including street lighting which are to be constructed following the Coast Engineering drawings attached with the ITT.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Fred Mence (Construction) Ltd£200kends (15 Oct 2020)

Details

What the buyer calls it
Ellington Phase 2, Adopted Roads and Drainage
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
15 Sep 2019
Work ends
15 Oct 2020

Who the buyer named

Mrs Kerry Davidson was the named contact on this notice.

Kerry.Davidson@northumberland.gov.uk