Skip to the main content
The Crier

Fire Safety Package E (Lawrence Weston and Fishponds)

Your saved contracts

What the buyer wrote

Remedial Fire Safety Works to Lofts, communal ducts & flats With associated asbestos removal. Works to be known as Compartmentation Package E blocks.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Complete Fire Protection£189.2kends (31 Mar 2020)

Details

What the buyer calls it
Fire Safety Package E (Lawrence Weston and Fishponds)
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Suitable for small firms
The buyer says yes. What that is worth
Work starts
2 Dec 2019
Work ends
31 Mar 2020

Who the buyer named

Carrie Pearson was the named contact on this notice.

carrie.pearson@bristol.gov.uk