What the buyer wrote

Further comp from Civil Engineering from 50k to 500k Works are defects potholing for the period 23 March to 30th September 2020

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Pinkney Building Contractors Ltd£134.6kends (30 Sep 2020)

Details

What the buyer calls it
Further Competition - 4x2 Gangs Pothole Defects Package 1
How they are buying
The buyer did not say
Type
works
Work starts
16 Mar 2020
Work ends
30 Sep 2020
Kind of work
Construction

Who the buyer named

Donna Iley was the named contact on this notice.