What the buyer wrote
The Enoch House refurbishment project is a scheme to convert 45 bed-sits and flats in a 1970’s built sheltered housing complex into 37 one and two bedroom flats to a high standard of finish and improved thermal efficiency.The project, which has an estimated cost of approximately £4Million is planned to be carried out in phases over 18 months from April 2015 to October 2016.The principle contractor will be Colchester Borough Homes (CBH) and we are looking to appoint suitably experienced and qualified contractors to carry out the work to this Colchester Borough Council property.The building will be partially occupied by residents throughout the duration of the project so great care, sensitivit…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- GB-Colchester: Refurbishment of Enoch House
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 30 Jun 2015
- Work ends
- 31 Dec 2016
- Kind of work
- Supplies and catering, New build construction, Refurbishment and fit-out, Civil engineering and groundworks, Roofing, windows and building fabric, Electrical installation, Heating, plumbing and mechanical, Building surveying and inspection, Security guarding and monitoring, Renewables and building decarbonisation, Logistics, courier and distribution
Who the buyer named
Matt Howe was the named contact on this notice.