What the buyer wrote

The project comprises the removal of asbestos and full internal refurbishment of approximately 1/3 of the Second Floor of South Tower as part of Phase 1. Key dates are as follows : Date for Commencement of the works- Monday 5th March 2018 Date for Completion of the works- Friday 30th March 2018 Tendering contractors are required to confirm their ability to comply with these dates as part of their tender submission. Works will be carried out under the JCT Minor Works Contract with Contractor's Design (2016).

Details

What the buyer calls it
GB-Derby: Refurbishment of 2nd Floor, South Tower
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
5 Mar 2018
Work ends
30 Mar 2018

Who the buyer named

Alex Lawrence was the named contact on this notice.