What the buyer wrote

Lighthouse construction work at Start Point. Main requirement is to carry out various groundworks at the lighthouse. The works are part of the modernisation project, which involves installing a new power cable and water pipe for the bore hole. There is also a requirement for some groundworks to facilitate the installation of a new power cable into the lighthouse.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Peninsula Access Ltd£139.4kends (28 Feb 2018)

Details

What the buyer calls it
GB-London: T0363 - Start Point Bore Hole Project
How they are buying
The buyer did not say
Type
works
Work starts
1 Nov 2017
Work ends
28 Feb 2018

Who the buyer named

The buyer published a contact address on this notice.