What the buyer wrote
NOTE: This notice was updated on 24 January 2020 for the following reason: Expression of Interest extended to 06th February 2020(The project consists of decommissioning and removing an existing sewage treatment plant and installing and commissioning a new sewage treatment plant and associated pipework and replacing most of the existing outfall pipework. The site is currently occupied and will need alternative means for dealing with the foul water arisings during the works.) Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solel…
Details
- What the buyer calls it
- GB-Shepton Mallet: MW1946 STP
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 24 Feb 2020
- Work ends
- 10 Apr 2020
- Kind of work
- Construction, Water, drainage and flood management
Who the buyer named
Tom Newman was the named contact on this notice.