GB-Stockton on Tees: PS386-11.16 Energy Centre
What the buyer wrote
The scope of works is to replace the existing boiler room with a new energy centre which will be more reliable, more energy efficient and more environmentally friendly. Once the new energy centre is up and running, the existing will be decommissioned and demolished. Additional information: Further competition under 2015/S 249-455273
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- GB-Stockton on Tees: PS386-11.16 Energy Centre
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 27 Apr 2017
- Work ends
- 30 Apr 2018
- Kind of work
- New build construction, Heating, plumbing and mechanical
Who the buyer named
Brad Symcox was the named contact on this notice.