The work comprises the demolition of 29no dwellings situated off Hawthorn Avenue, Hull. Dwellings are in blocks and are of a traditional brick build. It is assumed the properties are built on strip foundations, demolition is to include both the superstructure and sub structure down to a depth of 1 metre and include all pipework and drainage within the perimeter of the site. Post demolition the site will be backfilled with clean imported sub-soil to ground level. The existing boundary walls to the perimeter of 35 Stirling Street shall be re-built and newly exposed gable brickwork shall be repaired to ensure integrity is maintained.
Details
- What the buyer calls it
- GWH19 - Demolition of Hawthorn Avenue
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 21 Jul 2019
- Work ends
- 6 Sep 2019
Who the buyer named
Leila Oxtoby was the named contact on this notice.