To undertake trial investigation holes in 9 locations along Queen Alexandra Road, excavating by hand to dimensions provided, breaking out concrete kerbs, kerb haunch, pavement /footway construction, reinstating with type 1 back fill, sand and macadam, replacing with concrete kerbs as necessary. Works undertaken during normal working hours. Provide pedestrian barriers and signage around excavations.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Eurovia Contracting£11.5kends (5 Sep 2017)

Details

What the buyer calls it
High Wycombe Town Centre Masterplan (HWTCMP) - Alternative Route Phase 4 - Enabling Works - Trial Hole Investigation Works
How they are buying
Given to one supplier, no competitionNobody else was asked, and the buyer has to be able to justify that.
Type
services
Suitable for small firms
The buyer says yes. What that is worth
Work starts
27 Aug 2017
Work ends
5 Sep 2017

Who the buyer named

Jenny O'Neill was the named contact on this notice.