Highway Maintenance - Footway Slurry Seal Preparatory Works 2014-15 - Batch 2
What the buyer wrote
Footway Preparatory Works for Footway Slurry Seal. Additional information: Expressions of interest to be submitted by 03/07/2015. Please refer to the ITT document for details. Please note that there is a pass/ fail element to the tender. The contract will then be awarded to the contractor deemed to represent the most economical and advantageous tender using the following evaluation model: · Price 70% · Quality 30% Please also note that this Opportunity may have been advertised on other web portals, however, Supplying the South West is the only portal which includes all the relevant documents required to respond to this opportunity. It is a requirement that you 'Register interest' to provi…
Details
- What the buyer calls it
- Highway Maintenance - Footway Slurry Seal Preparatory Works 2014-15 - Batch 2
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 13 Sep 2015
- Work ends
- 16 Oct 2015
Who the buyer named
Debbie Samuel was the named contact on this notice.