What the buyer wrote
The works comprise of removing the existing block paving and Street furniture over the whole width of the Street and laying new Granite kerbs and Granite slabs and blocks on the new footway areas. The running lane will have full depth reconstruction in Bitmac. Works also include new drainage and gullies in the footway and carriageway including new sections of carrier drain to connect into the existing network. New street furniture will be installed including bollards, bins and benches.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Highways Framework Call-Off - Fleet Street Phase Three
- How they are buying
- The buyer did not say
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 8 Jan 2018
- Work ends
- 29 Jun 2018
- Kind of work
- Construction, Water, drainage and flood management
Who the buyer named
Lawrence Brown was the named contact on this notice.