This opportunity is for the HS2 box piling and diaphragm wall on the Old Oak Common Station HS2 project. Scope overview: Diaphragm Wall: Approx. 2km worth; - 1.2-1.5m thickness; - depth of 30m Piling: - Approx: 190 under reamed piles (with plunge columns); - 200 straight shafted - Pile dia. 1.8 - 2.4m - Under ream dia. 6.4 - 7.2m Working Hours: Monday - Friday 08:00 - 18:00 Saturday - 08:00 - 13:00 Current Main Works Programme: approx. 10 months on-site Programme commencement of 28/09/20 The ability and experience of suppli…

Read all of it on Contracts Finder →

Details

What the buyer calls it
HS2 Old Oak Common Station - Box Piling and Diaphragm Wall
How they are buying
The buyer did not say
Type
works
Work starts
8 Jan 2020
Work ends
31 Jul 2021

Who the buyer named

Manish Tailor was the named contact on this notice.