What the buyer wrote
Main objective: Civil Engineering (Maritime specialist) to underake design, contract administration, lead consultant, and principal designer duties The main objective of the proposed project is to stabilise the sea defences around the Hurst Castle for the medium term future (Approx. 30 years with ongoing maintenance) focusing on the priority areas. It is likely that without intervention the current levels of shingle may be eroded by the sea, undermining the outer walls and possibly leading to a collapse and loss of historic fabric. Additional information: Is a Recurrent Procurement Type? : No
Details
- What the buyer calls it
- Hurst Castle Sea Defences
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- services
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 1 Mar 2017
- Work ends
- 30 Oct 2018
Who the buyer named
Frances Ryder was the named contact on this notice.