What the buyer wrote
The works generally comprise of the modernisation and renewal of all lift main components to include, lift pumps and motors, control systems, car and landing entrances, lift car interior, complete rewire with new indication and control devices. Works also include the option of provision of temporary stairlifts for the duration of the works.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- M1920-19 Lift Modernisation - Trevett House
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 11 Nov 2019
- Work ends
- 31 Mar 2020
Who the buyer named
All communication to be via Delta was the named contact on this notice.