The Mining Remediation Authority have two Mine Water Treatment Scheme (MWTS) sites with solar PV installed that have missing or damaged solar panels. The sites are Dawdon MWTS and Bates MWTS. Both of these sites share the same 270w solar panels, in terms of manufacturer and model number. We would like to relocate missing panels from Dawdon MWTS with panels located at Bates MWTS. Sourcing rationale A total of four quotes were requested and three were received from local SMEs. A comparison matrix was compiled, assessing cost, capacity, and overall suitability to determine the best fit supplier. This approach was selected over a full tender process as the contract value falls below the releva…

Read all of it on Find a Tender →

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

AR Power£33.1kends (31 Oct 2025)

Details

What the buyer calls it
Mine Water Treatment Scheme (MWTS) - Panel Relocation
How they are buying
Given to one supplier, no competitionNobody else was asked, and the buyer has to be able to justify that.
Work starts
30 Sep 2025
Work ends
31 Oct 2025
Where
in the East Midlands

Who the buyer named

The buyer published a contact address on this notice.