HSE have a requirement to re-purpose an existing structure onsite for use as a façade fire test facility. The structure will be used for experimental projects studying fire spread over the external walls of buildings. Any type of façade construction may need to be tested and so the system has been designed to allow for this. The work required to achieve the objectives of this work, is to install a series of steel beams on to which standard sized fireboards can be attached. The works are required at our Buxton site SK17 9JN

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Build 4 Growth Ltd.£46kends (26 Sep 2025)

Details

What the buyer calls it
Modification Works to Building 68A (Facade Test Structure) at HSE Laboratory in Buxton
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
29 Jun 2025
Work ends
26 Sep 2025
Where
in the North West
Kind of work
Construction

Who the buyer named

Gary Owens was the named contact on this notice.