What the buyer wrote

Appointment of a contractor to build a Modular Building at the University of Birmigham

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Wenick Building Ltd£600kends (1 Dec 2018)

Details

What the buyer calls it
Modular Building - Temporary Office Accommodation - Main Contractor
How they are buying
Quotes from a few suppliersThe buyer approached a small number directly rather than advertising it.
Type
works
Work starts
1 Dec 2017
Work ends
1 Dec 2018
Kind of work
Construction

Who the buyer named

Karen Manyika was the named contact on this notice.