What the buyer wrote
This is a works contract.The Contract Form is the NEC 3rd Edition Engineering and Construction Contract(Option A) to undertake the NEQ main Works incorporating the required University amendments. The procurement procedure was Competitive Procedure with Negotiation and incorporated a pre-qualification stage incorporating de-selection to a maximum of five economic operators, ITT stage 1 with de-selection to two economic operators for final ITT stage 2.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- North East Quarter
- How they are buying
- Advertised, then negotiatedThe buyer talked terms with bidders rather than taking fixed offers.
- Type
- works
- Work starts
- 24 Jan 2018
- Work ends
- 29 Feb 2020
- Kind of work
- Construction
Who the buyer named
Ben Waters was the named contact on this notice.