North Portsea Island Coastal Defence Scheme - Phase 3: Tipner Lake - AWARD
What the buyer wrote
Portsmouth City Council - the 'Authority' - is embarking upon a major programme of coastal defence construction. The programme of works is part of the North Portsea Island Coastal Flood Defence Scheme which aims to reduce the risk of coastal flooding and erosion to the area over the next 100 years. The Authority is now seeking to appoint a contractor via this procurement exercise to deliver Phase 3 of the programme which will cover flood defence works at Tipner Lake from the Mountbatten Centre, Twyford Avenue to the Ports Creek Roundabout. The Tipner Lake works will consist of the construction of a new reinforced concrete seawall along the full length of this …
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- North Portsea Island Coastal Defence Scheme - Phase 3: Tipner Lake - AWARD
- How they are buying
- Advertised, shortlist firstSuppliers applied to be considered, and the buyer picked who went on to bid.
- Type
- works
- Work starts
- 31 Mar 2017
- Work ends
- 1 Feb 2019
Who the buyer named
Procurement Service was the named contact on this notice.