What the buyer wrote
The project involves the refurbishment of the whole of North Tower ,7th & 6th Floors including the circulation/ corridor areas of N8,N6, East Tower 5th floor & E805. Although N7 corridor space was refurbished in 2015, it will need modification to reflect the proposed changes on N7 generally. The project includes, but is not limited to, the careful isolation of M&E services, removal of redundant mechanical & electrical services, removal & encapsulation of asbestos containing materials; removal & carting away of furniture, floor finishes & existing vertical blinds. Demolitions of masonry walls; room remodelling, plastering, new suspended ceilings, new LED lighting; decorations, supply, i…
Details
- What the buyer calls it
- North Tower 8th Floor Laboratory Refurbishment
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 15 May 2016
- Work ends
- 12 Sep 2016
Who the buyer named
The buyer published a contact address on this notice.