Old Oak Common Station - Box Station Piling & Diaphragm Wall
What the buyer wrote
This opportunity is for the HS2 box piling and diaphragm wall on the Old Oak Common Station HS2 project. Scope overview: Diaphragm Wall: Approx. 2km worth; - 1.2-1.5m thickness; - depth of 30m Piling: - Approx: 190 under reamed piles (with plunge columns); - 200 straight shafted - Pile dia. 1.8 - 2.4m - Under ream dia. 6.4 - 7.2m Working Hours: Monday - Friday 08:00 - 18:00 Saturday - 08:00 - 13:00 Current Main Works Programme: approx. 10 months on-site Programme commencement of 28/09/20 The ability and experience of suppli…
Details
- What the buyer calls it
- Old Oak Common Station - Box Station Piling & Diaphragm Wall
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 8 Jan 2020
- Work ends
- 31 Jul 2021
Who the buyer named
Manish Tailor was the named contact on this notice.