Overhead Container Crane for an Intermediate Level Waste (ILW) Unshielded Store Extension to the Dounreay Cementation Plant (DCP)
What the buyer wrote
Dounreay Site Restoration Limited (DSRL) have awarded a contract for the design, procurement, manufacture, testing, installation and commissioning of an Overhead Container Handling Crane for the unshielded waste store extension to the Dounreay Cementation Plant (DCP). The scope of works comprises of the following activities: Scheme and Detail Designs which includes interactions with the Design Consultant appointed for the Build Phase; Procurement of components and systems; Manufacture of the crane; Fabrication, Assembly & Testing of the crane; Delivery of the crane to the Dounreay Site; Liaison with the Build Contractor for the Build Phase for the installation of the crane (i.e. rail …
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Overhead Container Crane for an Intermediate Level Waste (ILW) Unshielded Store Extension to the Dounreay Cementation Plant (DCP)
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- goods
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 29 Oct 2018
- Work ends
- 7 Nov 2020
Who the buyer named