What the buyer wrote
The steam pipework in the main building service floor is in very poor condition and must be replaced. The priority task is the replacement of the High and Low pressure lines that link the east to the west wing. This is urgent and identified as a potential risk by both the Competent Body (Allianz) and HSE.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- PHE - Corporate - Porton Steam Pipework
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 4 Mar 2019
- Work ends
- 31 Jul 2019
- Kind of work
- Quantity surveying and cost consultancy
Who the buyer named
Richard Blake was the named contact on this notice.