Principal Designer and Principal Contractor for the design and repair of Sherwood Lake dam bank
What the buyer wrote
Tunbridge Wells Borough Council (TWBC) are looking to procure the services of an experienced marine contractor to design and implement a repair solution for a leaking bank at Sherwood Lake dam wall. Whilst the lake wall acts as a dam the lake does not fall under the Reservoirs Act 1975 as it only holds 10,000 cubic meters of water and not the minimum 25,000 cubic meters for the act to apply. To view this notice, please click here: https://www.kentbusinessportal.org.uk/delta/viewNotice.html?noticeId=996617972
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Principal Designer and Principal Contractor for the design and repair of Sherwood Lake dam bank
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Work starts
- 9 Dec 2025
- Work ends
- 28 Feb 2026
- Where
- in the South East
- Kind of work
- Construction, Building surveying and inspection
Who the buyer named
Miss Louisa Coley was the named contact on this notice. Questions closed on 7 Nov 2025, 12:00 GMT.