Skip to the main content
The Crier

Project continuation for design and creation of Build Station

Your saved contracts

What the buyer wrote

Continuation of work where BAE Systems had originally undertaken an initial design phase for this work. This project will now need to continue with BAE Systems and Electroimpact owing to the existing design IP and technical knowhow owned by Electroimpact as carried out in a precursor project that the AMRC were not involved with.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

ElectroImpact UK Ltd£50kends (18 Jul 2020)

Details

What the buyer calls it
Project continuation for design and creation of Build Station
How they are buying
Given to one supplier, no competitionNobody else was asked, and the buyer has to be able to justify that.
Work starts
18 Jul 2019
Work ends
18 Jul 2020

Who the buyer named

Lynne Ford was the named contact on this notice.

lynne.ford@sheffield.ac.uk