Provision of new field water supply at Barton Hills NNR, Bedfordshire
What the buyer wrote
The work is to provide a new drinking water supply for grazing animals at Natural England's (NE) Barton Hills National Nature Reserve (NNR). See Appendix 1 for site photos. This requires the installation of approximately 1km of water pipe, laid through fields and woodland and crossing Church Road. The contractor will also provide and install all the necessary fittings including the provision of 2 galvanised water troughs. Your tender should provide alternative methodology and costings to allow for: a) Use of open trench installation with low ground pressure vehicles and equipment to avoid damage to both farmland and the nature reserve. b) Use of horizontal directional drilling te…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Provision of new field water supply at Barton Hills NNR, Bedfordshire
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 4 Dec 2017
- Work ends
- 23 Feb 2018
Who the buyer named