What the buyer wrote
The works comprise the removal of the existing copper sheet, stramit board, clips and fixings. The supply and fixing of new Vieo steel sheet system in a warm roof configuration to give a U Value of 0.18 W/m2K. All as manufactured, specified and supplied by Euro Clad. Additional information: Is a Recurrent Procurement Type? : No
Details
- What the buyer calls it
- RE-ROOFING OF THE WAGER BUILDING - Euro Clad
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Work starts
- 31 May 2018
- Work ends
- 1 Oct 2018
- Kind of work
- Roofing, windows and building fabric
Who the buyer named
Martin McMahon was the named contact on this notice.