Refurbishment of Ward 1 - Short Stay Surgical Unit
What the buyer wrote
Refurbishment of the Ward 1 - Short Stay Surgical Unit toilets and wash areas. Works are to be carried out in such a manner that safe access for Hospital Staff and the public is maintained at all times during normal working hours. The Contractor is required to produce a fixed programme for the design and completion of the works. The Contractor will make due allowance for all shutdowns and holiday periods.
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Refurbishment of Ward 1 - Short Stay Surgical Unit
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 20 Oct 2016
- Work ends
- 2 Dec 2016
- Kind of work
- Refurbishment and fit-out
Who the buyer named
Aisha Adekunle was the named contact on this notice.