What the buyer wrote

Restoration or replacement of posts and railings. Previous granite coping stones washed into the sea to be salvage and re-bedded in mortar. New granite stones to be fitted where old cannot be reused. Contractor to design screen/hoarding to segregate works from public. Additional information: This is a mini competition from a closed framework.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Hall Construction Services£618.8kends (31 May 2018)

Details

What the buyer calls it
Restoration of Roker Pier railings and coping stones
How they are buying
The buyer did not say
Type
works
Work starts
19 Jul 2017
Work ends
31 May 2018