What the buyer wrote
Pile Setting out/As-Built Dimensional Control at numerous locations along the M40 corridor. Commencing Summer 2020 until Winter 2024 Ideally works to be let in Five packages - there is the opportunity to apply for more than one package. Suppliers will be assessed on various factors including, but not limited to, Quality, Safety, Experience, Adding Value. Small Medium Enterprises are actively encouraged within this Project and the promotion of innovation and sustainable working practices. Bauer Keller is a Joint Venture formed from two of the World's Largest Specialist Geotechnical Contractors. The Joint Venture allows both comp…
Details
- What the buyer calls it
- Setting Out - Stage 2
- How they are buying
- The buyer did not say
- Type
- services
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 31 Aug 2020
- Work ends
- 6 Sep 2023
Who the buyer named
Ian Dales was the named contact on this notice.