SLaMT2016-025 - Bethlem LV Switchgear Project
What the buyer wrote
The purpose of this project is to: Replace substation A LV switchboard complete with mains synchronising capability and temporary generator connection facility. Provide a mains/generator changeover switchboard in LV switch room D complete with mains synchronising capability and temporary generator connection facility. Provide a temporary generator connection facility on the substation B LV switchboard. Amend the changeover controls on substation B LV switchboard to allow mains synchronising. Replace existing generator controls for substation A, B and D to allow mains synchronising and power export. Provide facilities for Demand Response remote starting and connection of generators in s…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- SLaMT2016-025 - Bethlem LV Switchgear Project
- How they are buying
- The buyer did not say
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 5 May 2017
- Work ends
- 28 Feb 2018
Who the buyer named
Procurement Team was the named contact on this notice.