Stamford Brook Sewer Diversion Works - Old Oak Common (S4) Station - HS2
What the buyer wrote
Stamford Brook Sewer Diversion Diversion of the Stamford Brook Sewer at the Old Oak Common site, including the Micro Boring works under the Great West Main Line and North Pole Depot New 1200mm int. dia. sewer that runs within central box footprint, supported at ground level within a reinforced concrete trough (R.C Trough provided by others. Construction of two deep manholes, including live connection to existing Thames Water 'egg' sewer. New 1200mm int. dia. sewer that will be pipe jacked under the GWML tracks and North Pole Depot from a launch pit located within the Wormwood Scrubs to a receiving pit connecting the sewer to Phase 2. Length of Pipe Jack 1…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Stamford Brook Sewer Diversion Works - Old Oak Common (S4) Station - HS2
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 16 Mar 2020
- Work ends
- 26 Mar 2021
Who the buyer named
Manish Tailor was the named contact on this notice.